PRODUCTION CONTROL

Spread the love

PRODUCTION CONTROL – PART #1

Overview of series – Learning discrete manufacturing and understanding costing by setting up scenarios in dynamics 365.

Overview of this document – Here we are only discussing the production scenario which we will be testing in the ERP system.

Scenario………………………………………………………………………………………………………. 1

  1. ABC Gaming Laptop Production Scenario with Two Variants……………………………………………. 1

 

  1. ABC GAMING LAPTOP PRODUCTION SCENARIO WITH TWO VARIANTS

ABC Gaming Laptop product master has only two variants based on: –

 

These variants maintain the ABC Gaming Laptop context, with slight changes to:

 

Product Master: ABC Gaming Laptop Variants

 The ABC Gaming Laptop is a high-performance gaming laptop with the following base specifications:

Variant Options

 The product master defines two variants:

·  Variant 1 – ABC Gaming Laptop (14″, Silver, 16GB):

·   Variant 2 – ABC Gaming Laptop (15.6″, Black, 32GB):

Bill of Materials (BOM) with Costing

 BOM for ABC Gaming Laptop (14″, Silver, 16GB)

Component Quantity Unit Cost ($) Total Cost ($) Description
Motherboard 1 150.00 150.00 With AMD Ryzen 7 5800H and RTX 3060
RAM Module 2 30.00 60.00 8GB DDR4 3200 MHz (16GB total)
SSD Storage 1 80.00 80.00 512GB NVMe SSD
Display Panel 1 G0.00 G0.00 14″ FHD IPS, 144Hz
Keyboard Assembly 1 40.00 40.00 RGB backlit, anti-ghosting
Battery Pack 1 60.00 60.00 48Wh Li-ion battery
Chassis (Top, Silver) 1 48.00 48.00 Aluminium top cover, silver coating
Chassis (Bottom, Silver) 1 43.00 43.00 Aluminium base, silver coating

 

Cooling Fan 1 15.00 15.00 Thermal management fan
Heat Sink 1 20.00 20.00 Copper heat sink for CPU/GPU
Webcam Module 1 10.00 10.00 720p HD camera with microphone
Speakers 2 5.00 10.00 Stereo speakers
Wi-Fi/Bluetooth Module 1 25.00 25.00 Wi-Fi 6, Bluetooth 5.0
Power Adapter 1 30.00 30.00 65W USB-C charger
Screws and Fasteners 20 0.10 2.00 Various sizes for assembly
Thermal Paste 1g 2.00 2.00 For CPU/GPU thermal interface
Total BOM Cost 645.00

BOM for ABC Gaming Laptop (15.6″, Black, 32GB)

Component Quantity Unit Cost ($) Total Cost ($) Description
Motherboard 1 150.00 150.00 With AMD Ryzen 7 5800H and RTX 3060
RAM Module 2 55.00 110.00 16GB DDR4 3200 MHz (32GB total)
SSD Storage 1 80.00 80.00 512GB NVMe SSD
Display Panel 1 100.00 100.00 15.6″ FHD IPS, 144Hz
Keyboard Assembly 1 40.00 40.00 RGB backlit, anti-ghosting
Battery Pack 1 60.00 60.00 48Wh Li-ion battery
Chassis (Top, Black) 1 50.00 50.00 Aluminium top cover, black coating
Chassis (Bottom, Black) 1 45.00 45.00 Aluminium base, black coating
Cooling Fan 1 15.00 15.00 Thermal management fan
Heat Sink 1 20.00 20.00 Copper heat sink for CPU/GPU
Webcam Module 1 10.00 10.00 720p HD camera with microphone

 

Speakers 2 5.00 10.00 Stereo speakers
Wi-Fi/Bluetooth Module 1 25.00 25.00 Wi-Fi 6, Bluetooth 5.0
Power Adapter 1 30.00 30.00 65W USB-C charger
Screws and Fasteners 20 0.10 2.00 Various sizes for assembly
Thermal Paste 1g 2.00 2.00 For CPU/GPU thermal interface
Total BOM Cost 70G.00

BOM Notes

·  Color:

·  Configuration:

Route Operations with Costing, Batch Sizes, and Resources

 The assembly process is nearly identical for both variants, with minor changes:

$10/hour. The table includes the “Setup C Run Cost per Operation” column.

Operation Type Resource Batc h Size Setu p Time (hr) Run Time (hr/uni t) Setup s Run Cost per Operatio n ($) Setup Cost ($/uni t) Run Cost ($/uni t) Total Cost ($/uni t) Applie s To
Motherboa rd Preparatio n Roboti c ThermalBot

-1

200 0.50 0.033 Setup: 5.00,

Run: 0.33

0.025 0.33 0.36 Both

 

Componen t Installation Manua l Technician Team A 50 1.00 0.083 Setup: 10.00,

Run: 0.83

0.20 0.83 1.03 Both
Chassis Base Assembly Roboti c AssemblyB ot-2 150 0.75 0.05 Setup: 7.50,

Run: 0.50

0.05 0.50 0.55 Both
Cooling Fan and Battery Installation Manua l Technician Team B 100 1.00 0.067 Setup: 10.00,

Run: 0.67

0.10 0.67 0.77 Both
Display Panel Attachme nt (14″) Roboti c DisplayBot

3

200 0.50 0.033 Setup: 5.00,

Run: 0.33

0.025 0.33 0.36 Varian t 1
Display Panel Attachme nt (15.6″) Roboti c DisplayBot

3

200 0.50 0.05 Setup: 5.00,

Run: 0.50

0.025 0.50 0.53 Varian t 2
Keyboard and Webcam Installation Manua l Technician Team C 50 1.00 0.083 Setup: 10.00,

Run: 0.83

0.20 0.83 1.03 Both
Chassis Finishing (Silver) Roboti c CoatingBot

6

100 0.50 0.017 Setup: 5.00,

Run: 0.17

0.05 0.17 0.22 Varian t 1
Chassis Finishing (Black) Roboti c CoatingBot

6

100 0.50 0.025 Setup: 5.00,

Run: 0.25

0.05 0.25 0.30 Varian t 2
Final Assembly Roboti c AssemblyB ot-4 150 0.75 0.05 Setup: 7.50,

Run: 0.50

0.05 0.50 0.55 Both

 

Quality Assurance and Testing Manua l QA Team 25 2.00 0.167 Setup: 20.00,

Run: 1.67

0.80 1.67 2.47 Both
Packaging Mixed PackBot-5 C Pack Team 100 1.00 0.05 Setup: 10.00,

Run: 0.50

0.10 0.50 0.60 Both

Total Operation Costs

Indirect Costs

 Suppose we have only these two products produced and we have following indirect costs. Indirect costs are allocated per unit based on a production run of 100 units, with a slight increase for variant management.

Indirect Cost Item Total Cost ($) Cost per Unit ($) Description
Facility Rent 1,000.00 10.00 Monthly rent allocation
Utilities 500.00 5.00 Electricity, water, internet
Equipment Depreciation 800.00 8.00 Amortized cost of robotic arms, tools
Quality Control Software 200.00 2.00 Licensing for diagnostic tools
Worker Training 300.00 3.00 Ongoing training programs
Administrative Overhead 425.00 4.25 Management, HR, accounting, SKU tracking
Total Indirect Cost 3,225.00 32.25

Cost Calculation Notes

$0.83/unit.

$0.20/unit.

·         Operation Changes:

Indirect Cost Notes

 

Total Cost Summary Variant 1: 14″, Silver, 16GB

Cost Category Cost per Unit ($)
BOM Cost 645.00
Operation Cost 7.94
Indirect Cost 32.25
Total Cost 685.1G

 Variant 2: 15.6″, Black, 32GB

 

Cost Category Cost per Unit ($)
BOM Cost 709.00
Operation Cost 8.19

 

Indirect Cost 32.25
Total Cost 74G.44


Related posts

Microsoft Dynamics 365 Cash & Bank Management – Create Deposit Slips

by Mahmood Ul Hassan admin
2 years ago

Microsoft Dynamics 365 Fixed Assets-Create a Fixed Asset

by Mahmood Ul Hassan admin
2 years ago

Engineering Change Management 365 Finance

by Mahmood Ul Hassan admin
9 months ago
Exit mobile version